CABLE TRAYS IN BLAST LOCK NUMBER 1 COMPLEX 1A 9 NOVEMBER 1961
STEEL FRAMING COMPLETE FOR LIQUID OXYGEN PLANT 7 FEBRUARY 1961
LIQUID OXYGEN PLANT 5 APRIL 1961
ARRIVAL OF LIQUID OXYGEN TANK AT COMPLEX 1A 23 DECEMBER 1960
DESCENDING RAMP INTO EXCAVATED COMPLEX 1A 23 DECEMBER 1960
TURNING AND MOVING DOLLIES FOR LOX TANK COMPLEX 1A 23 DECEMBER 1960
LOX TANK ON PAD COMPLEX 1A 23 DECEMBER 1960
CENTRAL PNEUMATIC SYSTEM FOR MULTIPLE JACKING COMPLEX 1A 21 DECEMBER 1960
JACKING AND CRIBBING OPERATION COMPLEX 1A 21 DECEMBER 1960
|
|